MacArthur High School Renovation and Addition

MacArthur High School Renovation and Addition
Posted on 05/05/2017

The MacArthur Renovations and Addition package includes renovations of the existing restrooms, corridors, mini-gym, locker rooms, hallways, and classrooms, along with the addition of a 51,316 square-foot classroom wing.

High moisture content is present in the building pad, which is slowing down the progress for the drilled piers. Construction will continue with pier concrete pours, and the installation of the underground electrical and plumbing lines as the moisture dries. Alternative methods for the new building foundation are currently being priced. The installation of the storm water line to the detention pond is complete. Career and Technology Education equipment is being relocated in preparation for renovations, which is scheduled to begin in May of 2017.

MacAthur HS Addition