Summer renovations began at Carver High School with contractors mobilizing on June 6, 2016. The scope of work shall consist of demolition of items to be replaced, cabinet replacements, painting, lighting upgrades, carpet replacement, vinyl floor tile replacement, and new wall paneling in the corridors. The renovation work will take place in the front office, corridors, the cafeteria and several classrooms within the school. The work is scheduled to be completed at the end of the summer of 2016.

July 2016

The ceiling grid, cabinets and the vinyl floor tile demolition has been completed. The framing is in place to install the corridor wall panels. The painting has begun in the classrooms and office areas. The ceiling grid installs are in progress in the corridors and office areas. Preparations for painting and the vinyl floor tile replacement have begun. The book room preparations will begin soon.

Carver Front Entrance
Front Entrance
Carver Front Office
Front Office
Carver Principals Office
Principal's Office
Carver Corridor Renovations
Corridor Renovations
Carver Ceiling Grid
Ceiling Grid